How to Install Drywall
what you'll need
- Wallboard
- Keyhole Saw
- Reinforcing Tape
- Screws
- Drop Cloth
- Sandpaper Block
- Sandpaper
- Finishing Knife
- Trowel
- 1x4s and 2x4s for "T" Brace
- T-Square
- Crown-Head Hammer
- Joint Compound
- Adhesive
- Metal Corner Strips
- Steel Rule
- Trimming Knife
- Adhesive Gum
- Nails
- Estimating Materials Needed
- Advance Planning for Drywall Installation
- Cutting Drywall
- Vertical or Horizontal Installations
- Applying Drywall to the Ceiling
- Wall Application of Drywall
- Finishing Touches
ESTIMATING MATERIALS NEEDED HOW TO FIGURE A ROOM FOR DRYWALL You need the Flash plug-in to view animations. Click to install Flash. For example, if your room measures 14x16, this equals 14' + 14' + 16' + 16' = 60 or 15 wallboards required. To allow for areas such as windows, doors, fireplaces, etc., use the deductions listed below: deductions for each:
Perimeter No. of 4x8
Wallboards Needed
36' 9
40' 10
44' 11
48' 12
52' 13
56' 14
60' 15
64' 16
68' 17
72' 18
92' 23 
door : 1/3 wallboard (A)
window : 1/4 wallboard (B)
fireplace : 1/2 wallboard (C)
The actual number of wallboards for this room would be 13 pieces (15 pieces minus 2 total deductions). Always use the next highest number of wallboards when the perimeter total is between ranges shown in the table. These figures are for rooms with 8' ceiling heights or less.
Estimating Nails, Joint Compound & Tape
drywall thickness type of nail approx. lbs. per 1,000 sq.ft. of drywall
3/8", 1/2" 1-5/8" coated type drywall nail 5-1/4 lbs.
3/4" 1-7/8" coated type drywall nail 5-1/4 lbs.
drywall (square feet) est. amount of joint compound* est. amount of wallboard tape
100-200 sq.ft. 1 gal. 2-60' rolls
300-400 sq.ft. 2 gals. 3-60' rolls
500-600 sq.ft. 3 gals. 1-250' roll
700-800 sq.ft. 4 gals. 1-250' & 1-60'
900-1,000 sq.ft. 1-5 gal. pail 1-250' & 2-60' or 1-500' roll
* A powder joint compound is also available. Estimate 60 lbs. per 1,000 sq.ft. of wallboard.
ADVANCE PLANNING FOR DRYWALL INSTALLATION
-
Always start by making a sketch of the wall and ceiling areas to be covered before applying the drywall. A sketch enables you to detect errors on paper–not on the job.
-
Always install the wallboards perpendicular to (across) the joists on ceilings.
-
You should apply drywall to the ceiling first, then to the walls.
-
Use a special water-resistant drywall where excessive moisture may be a problem. In most cases, water-resistant drywall is covered with a green finish paper.
-
Install a special fire-rated (Type X) drywall where building codes require the use of a fire-rated material.
- If a vapor barrier is needed, use a special insulating, foil-backed wallboard, or create a vapor barrier with sheets of plastic material.
| CUTTING DRYWALL
|
| |
| | ||
| VERTICAL OR HORIZONTAL INSTALLATIONS
|
| |
| | ||
| APPLYING DRYWALL TO THE CEILING
|
| |
| | ||
| WALL APPLICATION OF DRYWALL
|
| |
| | ||
| FINISHING TOUCHES ON A DRYWALL INSTALLATION
| Click on drawing above to view animation.
| |
| | ||
Ask for Other "Show-How" Instruction Sheets
Check your state and local codes before starting any project. Follow all safety precautions. Information in this document has been furnished by the National Retail Hardware Association (NRHA) and associated contributors. Every effort has been made to ensure accuracy and safety. Neither NRHA, any contributor nor the retailer can be held responsible for damages or injuries resulting from the use of the information in this document.
Additional easy-to-use instruction sheets for home do-it-yourself projects are available from your local supplier of materials. Come in and ask for "Show-How" instructions when you get ready for that next handyman project!