Order of Work?

Reply

  #1  
Old 01-12-05, 06:47 AM
D
Member
Thread Starter
Join Date: Nov 2004
Location: New Jersey
Posts: 25
Received 0 Votes on 0 Posts
Order of Work?

I am in the process of finishing my basement. I am contracting, but having subs do work. I will have rough electric and framing inspections done in next 10 days..

In my town, next inspection is unsulation, then I can drywall. My question is...after drywayll, what is the best order to do the following:

a) Prime/paint
b) Doors/Trim
c) Final Electric
d) Carpet floor

I'm not sure If I should paint first or have electrician come first or what. Is there a generally accpeted order. My last inspection after sheetrock is final for all, so I just don't know which is best order..

Thanks for any help.
 
Sponsored Links
  #2  
Old 01-12-05, 07:19 AM
123456
Visiting Guest
Posts: n/a
I would think that you would not do the trim/carpet/ finish electrical until you have primed and painted. Otherwise you may have a mess on all of your trim out.
 
  #3  
Old 01-12-05, 02:11 PM
caleyg's Avatar
Member
Join Date: Nov 2003
Posts: 327
Received 0 Votes on 0 Posts
paint
electric
doors
carpet
trim

But some do trim before carpet, leaving a space under baseboards
 
Reply
Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Thread Tools
Search this Thread
 
Ask a Question
Question Title:
Description:
Your question will be posted in: