I am going remove and fill in a stone pathway that I put in years ago...reason is...getting tired of spraying for weeds.....what I need help in is....how do I figure out how much dirt to get....area is 12ft wide X 40ft long...as for depth..I am going to seed grass...so 2" to 4" (inches) I guess...I hope that this would be the same if I were to be doing cement....an answers will help...
 
Sponsored Links
  #2  
Old 07-15-08, 11:02 AM
N
Member
Join Date: May 2002
Location: Maryland zone 7
Posts: 1,716
Received 0 Votes on 0 Posts
Hi Bristo,

If I'm reading this right, you are going to remove the stone and fill the area with topsoil. Then you will seed. You should know the depth once you remove the stone. You will then be able to see the top of the soil line. Don't forget you will need to tamp down the soil before you seed. Here's a compost calculator that you can use once you start digging and know the depth.
http://www.cedar-grove.com/calculator.asp

Newt
 
  #3  
Old 07-15-08, 12:11 PM
Gunguy45's Avatar
Super Moderator
Join Date: Dec 2007
Location: USA
Posts: 21,113
Received 3 Votes on 3 Posts
If it requires a 4" fill, it would be about 6 cu yds of soil.

12 x 40=480 sq ft (or cu ft if it was 1ft deep)

divide by 3 (3 x 4"= 1ft) = 160 cu ft

divide by 27 (27 cu ft in 1 cu yd) = 5.92 cu yds
 
Reply
Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Thread Tools
Search this Thread
 
Ask a Question
Question Title:
Description: