OK to include "Junk" in Concrete Step Pour?

I just had a contractor remove a thick step and a small walkway with a jackhammer. Before pouring the new step, he included large chunks of the old concrete, presumably to save time, concrete and effort. Is this OK? Wouldn't it have been better to have all new, freshly-poured concrete? Did I get cheated?
 
  #2  
Old 09-06-08, 09:27 PM
Speedwrench's Avatar
Member
Join Date: Apr 2008
Location: Oklahoma
Posts: 1,602
Upvotes: 0
Received 0 Upvotes on 0 Posts
as long as it is no closer than 2 in to the surface it is good, should not cause any weakness at all.
no you did not get cheated.