Question on monolithic slab - Pour all at once?
#1
Member
Thread Starter
Join Date: Aug 2005
Location: Earth
Posts: 103
Upvotes: 0
Received 0 Upvotes
on
0 Posts
Question on monolithic slab - Pour all at once?
Hello
I am moving in to the second phase of the project. Thank you all sincerely who responded to my earlier post on whether to butt concrete slab to the siding. I have decided to pour the slab 7" below the siding. Now I have another question
The contractor quoted to pour all at once - the 15" X 24" footing, 3 feet retaining wall on two sides and the 20 X 32 feet slab. Is this feasible? Quotes received from other contractors split this into three days – one day each to pour the footings, wait for some time, and than pour the retaining wall, back fill, compact and finally pour the slab on a separate day.
Is this acceptable practice- Pouring all (footing, retaining wall and slab) in one pump?. I am concerned that it might develop cracks since this would be a one huge piece of structure. Also I thought that the better idea is to pour the footing first and let it get cured and than pour the rest since they all sit on top of footing. Now the guy who quoted monolithic slab is the lowest quote, also has excellent reputation, so I would like to know if this is a correct way.
Please enlighten me on this. Thanks
I am moving in to the second phase of the project. Thank you all sincerely who responded to my earlier post on whether to butt concrete slab to the siding. I have decided to pour the slab 7" below the siding. Now I have another question
The contractor quoted to pour all at once - the 15" X 24" footing, 3 feet retaining wall on two sides and the 20 X 32 feet slab. Is this feasible? Quotes received from other contractors split this into three days – one day each to pour the footings, wait for some time, and than pour the retaining wall, back fill, compact and finally pour the slab on a separate day.
Is this acceptable practice- Pouring all (footing, retaining wall and slab) in one pump?. I am concerned that it might develop cracks since this would be a one huge piece of structure. Also I thought that the better idea is to pour the footing first and let it get cured and than pour the rest since they all sit on top of footing. Now the guy who quoted monolithic slab is the lowest quote, also has excellent reputation, so I would like to know if this is a correct way.
Please enlighten me on this. Thanks
#2
Member
Join Date: Feb 2005
Location: USA
Posts: 1,306
Upvotes: 0
Received 0 Upvotes
on
0 Posts
You can do it either way. The monolithic slab is perfectly fine if the guy has the help to do it and the forms stay put and don't bulge. I'm sure he knows what he's doing.
As far as cracking...it will. Either way you do it. Just make sure that whoever installs it cuts in some crack control joints so it cracks where YOU want it to, not randomly throughout the slab.
I used to do a lot of monolithic slab/footings with no problems. Good luck.
As far as cracking...it will. Either way you do it. Just make sure that whoever installs it cuts in some crack control joints so it cracks where YOU want it to, not randomly throughout the slab.
I used to do a lot of monolithic slab/footings with no problems. Good luck.
#3
Member
Join Date: Dec 2008
Location: lancaster
Posts: 167
Upvotes: 0
Received 0 Upvotes
on
0 Posts
The contractor quoted to pour all at once - the 15" X 24" footing, 3 feet retaining wall on two sides and the 20 X 32 feet slab. Is this feasible? Quotes received from other contractors split this into three days – one day each to pour the footings, wait for some time, and than pour the retaining wall, back fill, compact and finally pour the slab on a separate day.
To pour a wall and vibrate that and the one side has been cut out for floor to meet wall I feel is nuts. To keep Crete from slowly going under that form is a full time job for a person for some time not to mention no expansion joints,
I used to do a lot of monolithic slab/footings with no problems.
Pour the footer and the wall can be done at once if you have your snap ties low enough and don't pour to juicy. The problem is no kicker at the bottom for stable plumb form,.
I would pour the footer then form the wall pull forms that day and rub up.
Now you have a wall to snap a chalk line for height on inside slab and felt expansion joint. For the slab I use screed rails and screw felt expansion onto the screed rails and the rails are 1" lower then the felt. NOW you have real expansion joints and can grove between them. Again all at once is begging to crack wherever it wants. Om a side note whats in the works for retaining wall drainage behind the wall?
#4
Member
Here is a link that may give you some ideas:
http://www.eere.energy.gov/buildings...s/db/35017.pdf
Installing the foundation is not the time to rush the job.
Bud
http://www.eere.energy.gov/buildings...s/db/35017.pdf
Installing the foundation is not the time to rush the job.
Bud
#5
Member
Join Date: Dec 2008
Location: lancaster
Posts: 167
Upvotes: 0
Received 0 Upvotes
on
0 Posts
Here is a link that may give you some ideas:
http://www.eere.energy.gov/buildings...s/db/35017.pdf
Installing the foundation is not the time to rush the job.Bud
http://www.eere.energy.gov/buildings...s/db/35017.pdf
Installing the foundation is not the time to rush the job.Bud
Don't sweat it. Its hard to believe what some contractors come up with for the customer