I fall under the 2006 IRC, this is for a 4' wall with 8" block (crawlspace foundation). It looks like the requirement for reiforcing is 2 #4 in the footing with #4 for vertical reiforcement in the wall every #" (don't have table in fornt of me). I don't see any mention of what is required to for the connection between the footing and CMU wall. How does the veritical reinforcement tie into the footing? Essentially, I want to know what needs to be in place before the footing is poured (and the foundation inspection).

I'm subbing this part out, I just want to make sure its done correctly.
 
  #2  
Old 08-09-10, 12:54 PM
Join Date: Jul 2009
Location: Central Virginia
Posts: 43
Upvotes: 0
Received 0 Upvotes on 0 Posts
Bents, angles, are tied to the horizontal rebar in the footing and extend above the top of the concrete footing. Allow for proper lap.
 
 