Rough Inspection Time
#1
Member
Thread Starter
Join Date: Feb 2003
Location: New Jersey
Posts: 197
Upvotes: 0
Received 0 Upvotes
on
0 Posts
Rough Inspection Time
Hi all,
I'm finally ready for my "rough inspection". The town didn't give me a whole lot of guidance as to what they'll be looking for. I've been following the good advice of people here, but I want to make sure I pass the first time around. I've followed the national and local codes with regard to outlet placement, stapling, lighting, etc. The town approved my plans. I've pulled wire to the main panel and subpanel as well as to all of the boxes and fixtures. I know this is vague, but what are some of the key things an inspector is going to look for during the rough inspection?
Thanks,
Jim
I'm finally ready for my "rough inspection". The town didn't give me a whole lot of guidance as to what they'll be looking for. I've been following the good advice of people here, but I want to make sure I pass the first time around. I've followed the national and local codes with regard to outlet placement, stapling, lighting, etc. The town approved my plans. I've pulled wire to the main panel and subpanel as well as to all of the boxes and fixtures. I know this is vague, but what are some of the key things an inspector is going to look for during the rough inspection?
Thanks,
Jim
#2

It is good that you have also obtained a copy of any amendments your town may have made to the NEC. Some local amendments have stricter requirements than the NEC. ( the NEC is minimum requirements) .One such requirement here locally is that only 2 outlets per 20 amp small appliance branch circuit. Another one is ,no wire smaller than # 12.
These rules all vary from one locale to another.
For a rough in here,all joints must be made up in boxes, grounds pigtailed out for device,etc. The inspector will be looking at wire sizes, box fill, routing of cables to prevent it
from being damaged during and after cover up, stapling, minimum amount of required outlets etc.etc.
Good Luck!
These rules all vary from one locale to another.
For a rough in here,all joints must be made up in boxes, grounds pigtailed out for device,etc. The inspector will be looking at wire sizes, box fill, routing of cables to prevent it
from being damaged during and after cover up, stapling, minimum amount of required outlets etc.etc.
Good Luck!
#3
Jim, you sound well prepared to me. I think you'll do just fine.
A few things to double-check: (1) metal plates where the cable might come within 1.25" of the stud face. (2) At least six inches of wire inside the box. (3) All but an inch or less of sheathing stripped inside the box. (4) Go ahead and preconnect your grounding wires with a green wire nut. In fact, preconnect everything except the wires that will attach to the switches and receptacles. (5) Wiring in place for required smoke detectors, complete with the signaling wire to the other detectors. (6) No damaged sheathing or insulation or nicked wires.
Good luck. It'll feel so good to pass. Have a beer and relax.
A few things to double-check: (1) metal plates where the cable might come within 1.25" of the stud face. (2) At least six inches of wire inside the box. (3) All but an inch or less of sheathing stripped inside the box. (4) Go ahead and preconnect your grounding wires with a green wire nut. In fact, preconnect everything except the wires that will attach to the switches and receptacles. (5) Wiring in place for required smoke detectors, complete with the signaling wire to the other detectors. (6) No damaged sheathing or insulation or nicked wires.
Good luck. It'll feel so good to pass. Have a beer and relax.
#4
Member
Thread Starter
Join Date: Feb 2003
Location: New Jersey
Posts: 197
Upvotes: 0
Received 0 Upvotes
on
0 Posts
Thanks for the replies.
I put nailing plates on every 2x4 that had a hole in it. At $0.20 each, I figured I'd err on the side of having them where they aren't required rather than the other way around. Everything else is out of harms way.
I haven't stripped the sheathing back yet, but I'll do that and attach the grounds over the next couple of days. Should I connect the breakers in the subpanel (obviously not the one in the main panel yet)?
Also, I noticed that the builder put a 2x4 between the studs just beneath the main panel and tacked all the wires to it. All my wires come from above on the subpanel - should I put a "nailer" like that above the panel to attach the wires to?
Thanks again,
Jim
I put nailing plates on every 2x4 that had a hole in it. At $0.20 each, I figured I'd err on the side of having them where they aren't required rather than the other way around. Everything else is out of harms way.
I haven't stripped the sheathing back yet, but I'll do that and attach the grounds over the next couple of days. Should I connect the breakers in the subpanel (obviously not the one in the main panel yet)?
Also, I noticed that the builder put a 2x4 between the studs just beneath the main panel and tacked all the wires to it. All my wires come from above on the subpanel - should I put a "nailer" like that above the panel to attach the wires to?
Thanks again,
Jim
#5
Romex, I mean Non-Metalic Sheathed Cable [non-metalic = not made out of metal, i.e. plastic, rubber, concrete, air, wood...] must be fastened within 12" of the box [except when fished in]. So if your cables are fastened to the studs in less than 12", then you're alright. Otherwise, this is a good way to conform to the Code.
~Peter
~Peter
#8
I could be wrong, but I don't think Jim's basement finish project is going to involve any new bonding to plumbing. What was put in when the house was constructed should still be good.
#9
Member
Thread Starter
Join Date: Feb 2003
Location: New Jersey
Posts: 197
Upvotes: 0
Received 0 Upvotes
on
0 Posts
Originally posted by John Nelson
I could be wrong, but I don't think Jim's basement finish project is going to involve any new bonding to plumbing. What was put in when the house was constructed should still be good.
I could be wrong, but I don't think Jim's basement finish project is going to involve any new bonding to plumbing. What was put in when the house was constructed should still be good.
So the subpanel is considered a "box". I'll put a "nailer" in place within 12" of it. Otherwise I think I'm good.....
Thanks,
Jim
#10
Somehow I overlooked the web address info about it being a basement project and had not looked at the pictures. My bad.
I'll be starting a new personal residence soon and would like to document the progress (or lack thereof) the way turbo has. What software are you using to build/maintain your web pages?
I'll be starting a new personal residence soon and would like to document the progress (or lack thereof) the way turbo has. What software are you using to build/maintain your web pages?
#11
Member
Thread Starter
Join Date: Feb 2003
Location: New Jersey
Posts: 197
Upvotes: 0
Received 0 Upvotes
on
0 Posts
Originally posted by txdiyguy
Somehow I overlooked the web address info about it being a basement project and had not looked at the pictures. My bad.
I'll be starting a new personal residence soon and would like to document the progress (or lack thereof) the way turbo has. What software are you using to build/maintain your web pages?
Somehow I overlooked the web address info about it being a basement project and had not looked at the pictures. My bad.
I'll be starting a new personal residence soon and would like to document the progress (or lack thereof) the way turbo has. What software are you using to build/maintain your web pages?
It sounds harder than it really is. It's been working nearly flawlessly for 3 years. I'd use one of those free web hosting companies but I hate PoP up ads and prefer the convenience of having everything stored locally.
Sorry you asked?

Jim
#12
Thanks. I imagine the hard part really is having the discipline to document regularly. I've built a number of houses and have done some pretty elaborate remodels and had planned to take lots of pictures along the way. But somehow I've never managed to do that.
#13
Member
Thread Starter
Join Date: Feb 2003
Location: New Jersey
Posts: 197
Upvotes: 0
Received 0 Upvotes
on
0 Posts
Originally posted by txdiyguy
Thanks. I imagine the hard part really is having the discipline to document regularly. I've built a number of houses and have done some pretty elaborate remodels and had planned to take lots of pictures along the way. But somehow I've never managed to do that.
Thanks. I imagine the hard part really is having the discipline to document regularly. I've built a number of houses and have done some pretty elaborate remodels and had planned to take lots of pictures along the way. But somehow I've never managed to do that.
If you have a digital camera, you've got it made. Most of my updates have been done in the wee hours of the morning before I go to work. I run down there, snap a few pics, modify the HTML files and I'm done. Takes about 10 minutes.
Good luck,
Jim