Electrical inspection question

Easy question. I hae a 70' run of conduit in a 18" deep trench. Will the inspector want to see the entire run or can I start to bury it it. Leaving the ends and a few sections in the middle uncovered.

TIA
 
Sponsored Links
  #2  
Old 12-22-18, 12:46 PM
PJmax's Avatar
Group Moderator
Join Date: Oct 2012
Location: Northern NJ - USA
Posts: 54,185
Received 475 Votes on 445 Posts
There is absolutely no set answer.
With a homeowner installation..... I'd recommend leaving the entire trench open.
 
  #3  
Old 12-22-18, 03:27 PM
Member
Join Date: Feb 2016
Location: United States, Virginia
Posts: 1,219
Received 26 Votes on 21 Posts
As said, best to leave it open. Also NEC calls for 18" of cover, so that's from the top of the conduit, not from the bottom of the trench.
 
  #4  
Old 12-22-18, 03:46 PM
Member
Thread Starter
Join Date: Jun 2001
Location: USA
Posts: 382
Received 0 Votes on 0 Posts
Thanks for the replies
I'm actually down 24"
 
Reply

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Thread Tools
Search this Thread
 
Ask a Question
Question Title:
Description:
Your question will be posted in: