Consolidating two two-gang boxes
#1
Member
Thread Starter
Join Date: Mar 2014
Posts: 7
Upvotes: 0
Received 0 Upvotes
on
0 Posts
Consolidating two two-gang boxes
I have two 2-gang boxes stacked a few inches apart. Between them they have four devices:
Here is a diagram of all the wires in both boxes (ground wires not illustrated):

My plan is to:
There's a few things that concern me:
Does any of this sound like a problem?
- Single-pole dimmer for chandelier
- Single-pole switch for outdoor light
- 3-way switch for can lights
- "Mystery" switch that apparently does nothing
Here is a diagram of all the wires in both boxes (ground wires not illustrated):

My plan is to:
- Remove the mystery switch entirely, capping off the red conductor in the lower box
- Relocate the chandelier dimmer into the lower box, in the spot vacated by the mystery switch. This should be especially easy, given that the switched wire from that device is in the lower box.
- Extend the 2-conductor cable that connects to the outdoor light with another
2-conductor cable, making the connections in the lower box, and extending the new wire into the crawl space and over to another location. - Eliminate the two short 2-conductor cables that connect the two boxes, since the upper right wire will replace the right one, and the upper left conductor can be extended to reach the lower box.
There's a few things that concern me:
- The white wire from the 3-conductor cable in the bottom left is connected via a wire nut to hot black wires. What the what? Is that okay?
- Based on the cable that the red wire from the mystery switch is part of (it heads up through the wall cavity, presumably towards the chandelier, which is switched by the black wire in the same cable), I'm guessing it used to be a switch wire for a ceiling fan that is no longer there. I'll have to investigate the attic to be sure, but if it's capped off at this end, there should be no problem, right?
Does any of this sound like a problem?
#2
Welcome to the forums!
Yes, but probably not anything you can't resolve.
Wrapping conductors, and conductor sets, in tape and running them through a wall cavity is not a compliant wiring method. The 2-conductor cable on the upper right is either the panel feed or a feed out to additional loads, and the 2-consuctor cable on the lower right is the mirror of that. Since those two sets must remain connected, you will have to find a different way to get the conductors from the upper right cable into the lower box.
I was going to suggest this if you hadn't.
Right. However, unless there is a splice box in the attic there will not be an accessible location to check there. This question is likely to only be answerable by removing the light fixture. I wouldn't bother. The reasoning is sound.
Since you have access to an attic above and a crawl space below this location you should be able to make splices in new boxes in either or both of those locations that will give you cables with complete jackets inside the wall while removing all line-voltage wiring from the upper box.
All openings in both boxes must be filled or closed when you finish. If that requires replacing one or both boxes then doing that will also give you access to the stud bay for working with both new and existing cables and your low-voltage wiring.
You didn't say which of the terminals on the 3-way switch is the common terminal. From your drawing, however, it appears that it would be the terminal that is on one side by itself, and that it is connected to the load. The two traveler terminals would be the two that are together on the other side of the switch. If so, then the white wire in the 3-conductor cable would be picking up the power for the 3-way pair and it would be connected to the common terminal on the other 3-way switch. It should be tagged with a bit of colored electrical tape or a permanent marker, in any color except gray or green, to designate that it is being used as an ungrounded (hot) conductor.
For now, could you check my guess on the connections on the two 3-ways and tell us whether working through the attic and crawl space will let you install continuous jacketed cables? Thanks.
Does any of this sound like a problem?
The conductors in the upper box are long enough to reach the lower box (although I'll have to tape up the conductors to replace the missing jacket, which is not long enough).
Remove the mystery switch entirely, capping off the red conductor in the lower box...Based on the cable that the red wire from the mystery switch is part of (it heads up through the wall cavity, presumably towards the chandelier, which is switched by the black wire in the same cable), I'm guessing it used to be a switch wire for a ceiling fan that is no longer there.
I'll have to investigate the attic to be sure, but if it's capped off at this end, there should be no problem, right?
Extend the 2-conductor cable that connects to the outdoor light with another
2-conductor cable, making the connections in the lower box, and extending the new wire into the crawl space and over to another location.
2-conductor cable, making the connections in the lower box, and extending the new wire into the crawl space and over to another location.
All openings in both boxes must be filled or closed when you finish. If that requires replacing one or both boxes then doing that will also give you access to the stud bay for working with both new and existing cables and your low-voltage wiring.
The white wire from the 3-conductor cable in the bottom left is connected via a wire nut to hot black wires. What the what? Is that okay?
For now, could you check my guess on the connections on the two 3-ways and tell us whether working through the attic and crawl space will let you install continuous jacketed cables? Thanks.
#3
Member
Thread Starter
Join Date: Mar 2014
Posts: 7
Upvotes: 0
Received 0 Upvotes
on
0 Posts
Welcome to the forums!
Wrapping conductors, and conductor sets, in tape and running them through a wall cavity is not a compliant wiring method. The 2-conductor cable on the upper right is either the panel feed or a feed out to additional loads, and the 2-consuctor cable on the lower right is the mirror of that. Since those two sets must remain connected, you will have to find a different way to get the conductors from the upper right cable into the lower box.
Since you have access to an attic above and a crawl space below this location you should be able to make splices in new boxes in either or both of those locations that will give you cables with complete jackets inside the wall while removing all line-voltage wiring from the upper box.
All openings in both boxes must be filled or closed when you finish. If that requires replacing one or both boxes then doing that will also give you access to the stud bay for working with both new and existing cables and your low-voltage wiring.
You didn't say which of the terminals on the 3-way switch is the common terminal. From your drawing, however, it appears that it would be the terminal that is on one side by itself, and that it is connected to the load.
If so, then the white wire in the 3-conductor cable would be picking up the power for the 3-way pair and it would be connected to the common terminal on the other 3-way switch.
It should be tagged with a bit of colored electrical tape or a permanent marker, in any color except gray or green, to designate that it is being used as an ungrounded (hot) conductor.
For now, could you check my guess on the connections on the two 3-ways and tell us whether working through the attic and crawl space will let you install continuous jacketed cables?
Thanks a million for your thoughtful and thorough reply!
#4
Originally Posted by Nashkat1
If so, then the white wire in the 3-conductor cable would be picking up the power for the 3-way pair and it would be connected to the common terminal on the other 3-way switch.
Originally Posted by Nashkat1
For now, could you check my guess on the connections on the two 3-ways...?
If there are 5 switches that control your chandelier now and everything is working fine, I would just tag that wire and make sure it winds up connected to the hot panel feed in the end. Also make sure that the common terminal on this 3-way winds up connected to the hot feed for the chandelier, even if you have to replace the top left cable run.
If only the painters hadn't sprayed gobs of tan-colored latex paint all over every conductor in the box, I might be able to tell. :-/
Originally Posted by Nashkat1
Since you have access to an attic above and a crawl space below this location you should be able to make splices in new boxes in either or both of those locations that will give you cables with complete jackets inside the wall while removing all line-voltage wiring from the upper box.
How about something like this Tyco Electronics Romex Splice Kit?
I also note that it says "NEC compliant - article 334-40b, 2005 & 2008 NEC." As I read it, Article 334.40(B) is almost as controlling of the installation method as it is of the manufacturing method. Here's the text, from the 2011 cycle:
334.40 Boxes and Fittings.
(B) Devices of Insulating Material. Switch, outlet, and
tap devices of insulating material shall be permitted to be
used without boxes in exposed cable wiring and for rewiring
in existing buildings where the cable is concealed and
fished. Openings in such devices shall form a close fit
around the outer covering of the cable, and the device shall
fully enclose the part of the cable from which any part of
the covering has been removed. Where connections to conductors
are by binding-screw terminals, there shall be available
as many terminals as conductors.
(B) Devices of Insulating Material. Switch, outlet, and
tap devices of insulating material shall be permitted to be
used without boxes in exposed cable wiring and for rewiring
in existing buildings where the cable is concealed and
fished. Openings in such devices shall form a close fit
around the outer covering of the cable, and the device shall
fully enclose the part of the cable from which any part of
the covering has been removed. Where connections to conductors
are by binding-screw terminals, there shall be available
as many terminals as conductors.
Last edited by Nashkat1; 03-30-14 at 10:52 PM.
#5
Member
Thread Starter
Join Date: Mar 2014
Posts: 7
Upvotes: 0
Received 0 Upvotes
on
0 Posts
If there are 5 switches that control your chandelier now and everything is working fine, I would just tag that wire and make sure it winds up connected to the hot panel feed in the end. Also make sure that the common terminal on this 3-way winds up connected to the hot feed for the chandelier, even if you have to replace the top left cable run.
- Tie the white conductor from the top left cable (which returns the neutral from the can lights) to (and only to) the white conductor in the bottom left cable
- Remove the remote end of that white conductor in the bottom left cable from the common terminal on the first 3-way switch, and tie it to the neutral in the box with that first 3-way switch
- Tie the common terminal on the first 3-way switch to a feed line on the same circuit as the neutral from step 2
As I said, I have no intention of doing this, since the circuit works as it should now, and the 6 can lights of 75W each use 450W or ~ 4 amps, and may overload whatever circuit they're added to. But in theory, this would work, yes?
What do you think?
#6
in theory, this would work, yes?
The can lights on the 3-way need the feed and neutral to come from the same circuit.
I wonder if the relevance of 334.40(B) is with respect to the "tap" function of the kit? If you're merely using it to splice two wires with the same number of conductors (there is a 3-wire version available as well as the one I linked), would any of the 334.40(B) language be relevant? It wouldn't be functioning as a "Switch, outlet [or] tap device[]"
OTOH, I'm wondering, since neither of us has seen one of these, whether it might be capable of connecting a tap.