Building Code for Cleanouts Through Fire Walls

What is the building code for cleanouts which extend through a fire wall into a garage area? My inspector came out last week and indicated I should change a 3" ABS downswept Y from the 2nd story, to a cast iron one. Can I just use a 3" cast iron/galvanized nipple with a 3" cast iron coupling and thread them into the 3" ABS cleanout? I will have to fur the wall out for this extension before drywalling, but I would have to fur out the wall anyway if I replace the ABS Y with cast iron, since CI fittings are larger dimensions.

I can provide a picture if it is necessary for clarity, Thanks, Iggy
 
Sponsored Links
  #2  
Old 11-29-04, 05:00 PM
Plumber2000's Avatar
Member
Join Date: May 2000
Location: Eugene, Oregon
Posts: 5,841
Received 0 Votes on 0 Posts
Call your inspector he will tell you one way or the other, he is there for guidance and will be happy to let you know.
 
  #3  
Old 11-30-04, 08:44 AM
Iggy's Avatar
Member
Thread Starter
Join Date: Feb 2004
Location: Southern California
Posts: 29
Received 0 Votes on 0 Posts
Thanks

Plumber 2000,
Thanks! I did call him and I can do it as I described. I guess the code says that the fire rated drywall must have cast iron at the point of penetration, which is what I thought was the point of his directive while on the job site. And your right, he was "happy" to help me.
 
Reply

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is On
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Thread Tools
Search this Thread
 
Ask a Question
Question Title:
Description:
Your question will be posted in: